Street & Sidewalk Construction Update

  • In 2015, City residents passed a ballot proposal to allow the City to collect 2.0 mills for street and sidewalk improvements. Since the passing, the City has worked aggressively to upgrade the 47 miles of street and 80 miles of sidewalk within the City.
  • Construction projects are subject to change depending on bid results and allocated funds. 
The Cost of Timely Maintenance
Proper street maintenance and surface preservation treatments at the right time (per PASER asset condition rating) is important to maintain the street surface condition, maximizing the impact of investment, while extending the life of the street asset.

2019 Project Map


2019 Mill/Overlay Streets

A “mill & overlay” is a street maintenance process that requires the removal of the top layer of a street by a milling machine. After the top layer is removed any road base repairs are completed. Before the new pavement is placed, the surface of the newly milled pavement is covered with a liquid asphalt tack coat to bond the old and new pavements before a new layer of bituminous pavement is put in place. Mill and overlay projects at various depths are designated for streets that meet PASER 2-4 ratings. Spot curb replacement, drainage issues and some ADA ramps are also typically addressed during mill/overlay projects. This type of work will be done in the following areas:

Phase 1
  • Woodcliff Circle (Hall to Lake) Completed.
  • Indian Trail (Bellclaire to end) Completed.
  • Greenwood Avenue/Barnard Street (Lakeside to Weathy) Completed.
  • Santa Monica Drive (Breton to Kenesaw) Completed.
Phase 2
  • Englewood Drive (Breton to Whitfield) Completed.
  • Woodlawn Avenue (Maplewood to City Limit) Completed.
  • Lake Grove/York Drive (Berwyck to Richards) Milling/paving was completed the week of June 17. Structures are in the process of being raised and restorations the week of June 24.
Phase 3
  • San Juan Drive/ El Dorado Drive (Argentina to Santa Cruz) Milling/paving was completed the week of June 17. Structures will be raised and restorations completed the week of June 24.
  • Alexander Road (Plymouth to City Limit, including intersection roundabout) Asphalt base paving was completed at the round about the week of June 17. Milling and paving the remainder of Alexander from the west city limit to Plymouth will take place the week of June 24.
  • Pinecrest Avenue (Elmwood to Heather) Milling/paving was completed the week of June 17. Structures will be raised and restorations completed the week of June 24.
  • Pinecrest Avenue (Argentina to Hall) Milling/paving was completed the week of June 17. Structures will be raised and restorations completed the week of June 24.

2019 Capeseal Streets

In the cape seal process an engineered polymer-modified RCRI is applied on the existing pavement and then covered with Micro-Surfacing. This is a cost-effective process that provides the strength and durability of RCRI and the smoothness and texture of micro-surfacing and/or slurry seal. A cape seal is applied when the pavement deterioration is greater than what a slurry seal or micro-surfacing is designed to correct, yet the pavement has not deteriorated to the point of requiring an expensive asphalt overlay. A cape seal prevents water penetration, reducing subsequent damage to the road bed, along with providing a new wearing surface. Cape seals are applied to streets rated PASER 4/5 to 6 depending on additional pavement surface maintenance. Cape seals can be used on residential streets as well as rural and urban highways. Used with crack sealing and necessary surface repairs, a cape seal significantly extends the life of a pavement. In advance of this treatment the City prepares the existing road surface by milling and paving out rough surface areas and performing crack sealing. This advance preparation work usually takes 1-2 days and is completed with appropriate traffic control. Once the advance preparation work has been complete for both the Capeseal and Micro-Surface streets, city contractors will arrive to apply the pavements during the month of June. Please expect traffic delays on these streets, and please be courteous and respectful of crews on site controlling traffic. This type of work will be done in the following areas:


  • Download 2019 Capeseal Project Map
  • SCHEDULE UPDATE: Please see the following link for remaining road work schedule https://drive.google.com/open?id=10swqC3ymsq2-R_TXvzNKmQfpriT0RgC5&usp=sharing (Dates in link will be updated if changed due to weather or equipment failures)
  • Northbound Plymouth Ave starting at Hall St and ending at Robinson Rd
  • Southbound Plymouth Ave starting at Robinson Rd and ending at Hall St
  • Eastbound Wealthy St starting at Gladstone Ave and ending at Lovett Ave
  • Westbound Wealthy St starting at Lovett Ave and ending at Gladstone Ave
  • Eastbound Lake Dr from Gladstone Ave to Hall St
  • Westbound Lake Dr from Hall St to Gladstone Ave
  • Eastbound and Westbound Reeds Lake Blvd from Manhattan Rd to EGR City Limits

2019 Micro-Surface Streets

Micro-surfacing, a cost-effective pavement maintenance process used by DOT's and municipalities across the country, is a design mixture of polymer-modified asphalt emulsion, crushed aggregate, mineral fillers, water, and additives. The mixture is properly proportioned, mixed, and uniformly spread over a suitably prepared surface. Micro-surfacing is a pavement preservation treatment for street surfaces rated at PASER 5 or 6. Micro-surfacing provides a quality wearing surface, extends pavement life, sets within a day, seals out moisture and does not require utility casting adjustments. In advance of this treatment the City prepares the existing road surface by milling and paving out rough surface areas and performing crack sealing. This advance preparation work will take place between May 6th and May 27th by city public works crews. Once the advance preparation work has been complete for both the Capeseal and Micro-Surface streets, city contractors will arrive to apply the pavements during the month of June. This type of work will be done in the following areas:
  • Download 2019 Micro-Surface Project Map
  • SCHEDULE UPDATE: Please see the following link for remaining road work schedule https://drive.google.com/open?id=10swqC3ymsq2-R_TXvzNKmQfpriT0RgC5&usp=sharing (Dates in link will be updated if changed due to weather or equipment failures)
  • Wilshire Drive (Hall Street to Breton Road)
  • Cornell Avenue (Wilshire Drive to City Limits)
  • Eastlawn Road (Boston Street to Heather Street)
  • Tenway Drive (Englewood Drive to City Limits)
  • Warwick Road (Tenway Drive to City Limits)
  • Englewood Drive (Tenway Drive to City Limits)
  • Albert Drive (Groton Road to Andover Road)
  • Conlon Avenue (Berwyck Road to End)
  • Darby Lane (Berwyck Road to End)
  • Vesta Lane (Berwyck Road to End)
  • Andover Road (Richards Drive to Hampshire Blvd)
  • Sherwood Avenue (Maplewood Drive to City Limits)
  • Ridgewood Avenue (Lake Drive to Maplewood Drive)
  • Edgewood Avenue (Lake Drive to City Limits)
  • Woodshire Avenue (Hall Street to Lake Drive)
  • San Jose Drive (Burchard Street to Hall Street)
  • Seminole Road (Fisk Road to City Limits)
  • Gladstone Avenue (Mackinaw Road to Alexander Drive)
  • Pontiac Road (Rosewood Drive to Gladstone Avenue)
  • Rosewood Avenue (Sherman Street to Franklin Street)
  • Gladstone Avenue (Reed Street to Franklin Street)
  • Belvedere Drive/Lake Pointe Drive (Edgemere Drive to Edgemere Drive)
  • Reeds Lake Blvd (El Centro Blvd to Rexford Drive)
  • Rexford Drive (Cascade Road to Reeds Lake Blvd)
  • Kingswood Drive (Cascade Road to End)
  • Frederick (End to End)

Sidewalk Construction 


As part of the 2015 Streets and Sidewalks Millage the City has been investing more funds into the annual sidewalk rehab and replacement program. Each year, targeted areas are investigated on a rotation basis. The targeted area is subject to budget constraints. 

Preventative Maintenance 


Streets that are not marked for construction this summer may still receive preventative maintenance if necessary. City DPW crews or contractors crack seal and/or apply mastic to PASER rated streets that are rated 6/7 throughout the spring and summer seasons. Please see the updated PASER map above for designated street ratings.

Manhattan Road Sanitary Sewer Lift Station


Work on the Manhattan Road sanitary sewer lift station is tentatively scheduled to commence on May 28th. Work will be in the right-of-way and below grade. Traffic will be maintained and residents will still be allowed access to their home.

Notices

Notices are mailed to residents on affected streets in advance of any work. Notices will be posted below as they are being mailed out.
Mill and Overlay Street Construction Notice Spring of 2019
Yard Restoration Notice
Patching and Cape Seal Street Construction Notice Spring of 2019
Indian Trail Mill and Overlay Street Construction Notice 2019
Micro Surface Construction Notice 2019
Street Closure Door Hanger American Pavements 2019

Construction

Street & Sidewalk Millage 



On May 5, 2015, East Grand Rapids voters approved a 10-year, 2.0-mill Streets and Sidewalks Millage request. The city updates our progress towards our 70% goal each fall after the construction season to benchmark our progress. Below is a graph of our current progress.

PASER Rating Line Graph

  • Blue line shows road condition projection if no additional funding was received.  
  • Green line projects road conditions through the 10-year period of the Street & Sidewalk Millage using the additional 2.0 mills approved by East Grand Rapids voters. 
  • Red line shows current ratings with approved millage. 

DTE Private Utility Gas Main Projects 2019

DTE Energy will be conducting part of their Gas Renewal Project (GRP) this spring on Oakwood Drive in between Breton Road and Lake Grove Avenue and on Woodcliff Drive in between Hall Street and Oakwood Drive. Please download the links below for more information:
*Update: DTE crews will begin work on Monday, April 15, 2019, at the above mentioned location on Oakwood Drive. Signs will be placed out on Monday by DTE to advise local residents. Please download the links below for more information:

DTE Gas Main Project Oakwood Drive Spring 2019
DTE FAQ's
DTE Notice to Residents

For any questions or complaints, please call DTE at 616-551-2621.


 

Information Links:



Questions regarding the East Grand Rapids Streets & Sidewalk millage can be directed to 616-949-2110 or to City Clerk Karen Brower by email or to 750 Lakeside Drive SE, EGR MI 49506.